Emergency DFTO Thermal Oxidizer Fabrication for Recycling Emissions

Emergency DFTO Thermal Oxidizer Fabrication for Recycling Emissions
Summary:

An oil recycling company in the Southwest needed a new thermal oxidizer shell ASAP. This case study shows how KKI came through despite supply chain challenges.

Type of Work:
Rebuild, Repair, Retrofit
Type of Equipment:
Thermal Oxidizer
Process:
Recycling

Problem

An oil recycler had a failing thermal oxidizer. The internally insulated shell was deteriorating and nearing failure. Since the sub-systems such as fans, gas train, controls, and dampers were functioning well, a shell-only replacement was the least disruptive option. Lead time was a major concern due to potential catastrophic failure of the shell as well as the uncertain availability of metal during the 2021 supply chain challenges.

Photos: In Progess

No items found.

Click on a picture to enlarge

Thermal oxidizer shell was ready to ship in under 6 weeks

Solution

Kono Kogs was entrusted to fabricate, insulate and ship the replacement shell as quickly as possible, in hopes of a 6-8 week delivery. Steel and material needed for the shell manufacturing were secured prior to asking our customer to commit to the purchase. With the significant fabrication capability added at Kono Kogs since early 2021, including many modern forming and cutting machines and the great can-do attitude of our fabrication team, Kono Kogs was confident of success. We are grateful this first-time customer was willing to give us their trust.

Photos: After

No items found.

Click on a picture to enlarge

Equipment & Services Provided

Thermal Oxidizer

Results

The thermal oxidizer shell was ready to ship in under 6 weeks. This was a significant achievement considering the limited availability of drawings for this older system, and the 2021 supply chain challenges. Contact Kono Kogs for your emergency fabrication needs, machine assembly needs, and oxidizer repair & replacement needs.